 This is a map of candidate construction projects for TIP years 2018 - 2019. The projects here have been submitted by their respective municipalities for consideration for funding. The submitted projects were ranked by their Technical merits, reviewed by the ATRC Technical Committee, then approved by the Policy Committee for consideration for funding.  This list of projects is open for public comment for 30 days or until April 27.



RANK CITY LOCATION DESCRIPTION PROJECT CLASS MILES COST ESTIMATE
1 Lisbon Route 196  Grind & overlay from Capital Ave to Main St Resurfacing 1.00  $      600,000
2 Auburn Various Move traffic signal on Main St from Academy to Elm, modify Minot @Elm/High Intersection -  $      615,000
3 Auburn Broad Street Mill & fill from Mill St to Mill St w/sidewalk ramp ADA improvements Resurfacing 0.85  $      505,000
4 Auburn Route 4 @ Fair Street Reconstruct intersection with roundabout Intersection -  $  2,340,000
5 Lewiston Stetson Road Mill & fill from Main St to College St, w/culvert replacement @ Stetson Brook Resurfacing 0.66  $      265,000
6 Lewiston East Avenue Resurface from Homefield St to Fairlawn Ave with sidewalk improvements Resurfacing 0.38  $      800,000
7 Auburn Route 4 @ Lake Shore Dr Reconstruct intersection with roundabout Intersection -  $  2,340,000
8 Auburn Hotel Road Reconstruct from East Hardscrabble to Lewiston Junction Road Reconstruction 0.50  $  1,500,000
9 Lewiston Lincoln Street Construct multi-use path from Gulley Brook to LAWPCA Sidewalk 0.70  $      620,000
10 Lewiston River Road Mill & fill, reconstruct shoulders from South Ave to Razel Way Reconstruction 0.66  $      970,000
11 Lewiston River Road Reconstruct from Razel Way to Plourde Parkway Reconstruction 0.66  $  1,410,000
12 Auburn Lewiston Junction Road Hotel Road westward; relocation to accommodate runway Reconstruction 0.22  $  2,100,000
13 Auburn Rodman Road Overlay from Hotel Rd to Washington St Resurfacing 1.03  $      515,000
14 Auburn South Main Street Reconstruct from Bolster St to Sixth St Reconstruction 0.25  $  1,195,000
15 Auburn South Main Street Reconstruct from Sixth St to Broad St Reconstruction 0.16  $      575,000
16 Lewiston College Street Reconstruct from Russell St to Greene Town line Reconstruction 3.35  $  4,320,000
17 Auburn Lake Auburn Avenue Mill & fill from Turner St to Center St w/sidewalk ramp ADA improvements Resurfacing 0.50  $      375,000
18 Auburn Poland Road Overlay from Manley Rd to Pride Rd Resurfacing 1.07  $      515,000
19 Auburn Hotel Road Reconstruct from Stevens Mills Rd to Crest Ave Reconstruction 0.95  $  1,500,000
20 Auburn Hampshire Street Reconstruct from Turner St to Gamage Ave Reconstruction 0.45  $  1,000,000
21 Lewiston South Avenue Reconstruct from Lisbon Street to Lincoln Street Reconstruction 0.55  $  2,450,000
22 Lewiston Park Street Rehab from Main Street to Pine Street Rehabilitation 0.20  $      310,000
23 Auburn Gracelawn Road Reconstruct from Turner St to Mt Auburn Ave Reconstruction 0.85  $  1,200,000
24 Auburn Spring Street Mill & fill from Troy St to Elm St w/sidewalk ramp ADA improvements Resurfacing 0.43  $      340,000
25 Lisbon Village Street Mill & fill w/sidewalk improvements from Route 196 to Pinewoods Rd Resurfacing 0.36  $      600,000
26 Lewiston Bates Street Rehab from Oak St to Ash St; bike lanes, channelization islands for buses Rehabilitation 0.10  $        50,000
27 Auburn Summer Street Park Ave to Vining Street Resurfacing 1.15  $      280,000
28 Lewiston Scribner Boulevard Reconstruct from Pleasant St to Webster St Reconstruction 0.53  $      950,000